STEAM
All steam plumbing to and from the kettle and
steam boiler should be thoroughly cleaned and
inspected for dirt and debris before final
connection to the kettle are made.
Generally, kettles require 1/2" i.p.s. pipe, 10-45 psi
steam pressure. If the steam supply pressure
exceeds 45 psi, a pressure reducing valve is
required. The steam inlet is at the right side of the
kettle, as n from the front.
A pressure reducing valve is required on the
incoming line as shown below. The relief valve
should have a capacity of 300 lb/hr (136 kg/hr).
CONDENSATE (Kettles without SD Stands)
Maximum pressure rating on table-top kettles is
50psi. It is highly recommended that a pressure relief
valve equal to or less than this pressure be installed
on the incoming steam line close to the kettle.
A steam condensate trap must be plumbed to a drain,
using minimum 1/2" NPT plumbing. The condensate line
is limited to a maximum rise of 10 feet in order for the
steam pressure to adequately force the condensate
through the plumbing. Any higher rise requires a pump.
If the steam boiler to which this kettle is installed has a
condensate return (closed loop system), a 1/2" steam
strainer, a 1/2" steam trap, and a 1/2" check valve must
be installed on the output (condensate) side of the kettle.
CONDENSATE (Kettles c/w SD Stands)
The stand comes factory plumbed so the condensate
is connected to the stands drain manifold.
POTABLE WATER
The water faucet (optional on kettles purchased
without SD stands) with swing spout, requires 1/2
inch O.D. copper tube plumbing for hot or cold water
supplies to the faucet (SPK - cold water connection
only, DPK - hot and cold water connection).
FINAL INSTALLATION CHECK
1. Partially fill the kettle with water.
2. Slowly turn the steam supply valve's knob to
the open position.
3. Release the safety valve, ensuring that the
steam escapes freely. Stay clear of steam
exhaust when releasing the safety valve.
4.
Observe that the water in the kettle comes to a boil.
5. Close the steam supply valve.
6. Drain off the water by tilting the kettle.
PRESSURE
REDUCING
VALVE
RELIEF
VALVE
STRAINER
STEAM
TRAP
CHECK
VALVE
STRAINER
UNION
SHUT OFF
VALVE
MANUAL
STEAM
VALVE
CONDENSATE RETURN
STEAM
IN
UNION
TO DRAIN OR BOILER
CONDENSATE LINE
TO DRAIN (CONDENSATE RETURN PLUMBED TO 1 1/2" DRAIN MANIFOLD)
PRESSURE
REDUCING
VALVE
RELIEF
VALVE
STRAINER
SHUT OFF
VALVE
STEAM
IN
UNION
KETTLES
RECOMMENDED PIPING
SCHEMATICS
(all service connections shown supplied by others)
KETTLES c/w
SD STANDS